PROJ-2031 · Riverline Plaza

DRAW-2031 — draw request

Pinnacle Construction · Period Apr 11, 2026 – May 11, 2026

Requested
$142,000
This draw period.
Approved
$142,000
Approved May 12, 2026
Released (net)
$127,800
May 14, 2026
Retainage held
$14,200
10% per draw.
Percent complete
85.0%
From inspector report.
Schedule of values (12 line items)
AIA G703-style schedule. Inspector validates percent-complete per line.
#CostDescriptionScheduledThis periodTo date%Balance to finishRetain
103000Foundation - concrete, rebar & forming$320,000$0$320,000100%$0$0
203200Slab on grade & topping$185,000$0$185,000100%$0$0
304000Masonry - block & veneer$240,000$8,000$228,00095%$12,000$800
405000Structural steel framing$410,000$12,000$389,50095%$20,500$1,200
506000Rough carpentry & sheathing$220,000$22,000$198,00090%$22,000$2,200
607000Roofing & weatherproofing$165,000$26,000$132,00080%$33,000$2,600
708000Doors, frames & glazing$145,000$18,000$87,00060%$58,000$1,800
809000Drywall & interior finishes$195,000$14,000$117,00060%$78,000$1,400
915000Mechanical (HVAC) rough-in$280,000$20,000$196,00070%$84,000$2,000
1015400Plumbing rough-in & fixtures$175,000$11,000$122,50070%$52,500$1,100
1116000Electrical rough-in & panel$215,000$9,000$150,50070%$64,500$900
1202000Sitework, paving & landscaping$95,000$2,000$47,50050%$47,500$200
Totals (12 lines)$2,645,000$142,000$2,173,00085.0%$472,000$14,200
Lien waivers (5)
Required from each subcontractor with paid work this period. Waivers older than 60 days expire.
SubTypeSignedAmount throughStatus
Heartland Concrete
SUB-201 · concrete
Conditional progressMay 6, 2026$95,000Signed
Apex Steel & Framing
SUB-202 · framing
Conditional progressMay 6, 2026$78,000Signed
Voltage Electric
SUB-203 · electrical
Conditional progressMay 6, 2026$42,000Signed
Northwind Mechanical
SUB-204 · mechanical
Conditional progressMay 6, 2026$58,000Signed
Cedar Finishes Inc
SUB-205 · finishes
Conditional progressMay 6, 2026$33,000Signed
Inspections (1)
Independent field validation of percent-complete claims by line.
Hank Mendez
Visited May 8, 2026 · 4 photos
85.0%
Reviewed

Site walked with GC superintendent. All structural complete; finishes progressing on schedule. 4 photos attached.

Line findings
LineClaimedObservedVariance
SoV line100%100%0%
SoV line100%100%0%
SoV line95%95%0%
SoV line95%95%0%
SoV line90%90%0%
Approval chain
Loan officer → owner sign-off → finance releases. Senior lender required over $500,000.
StepRequired roleApproverDecidedDecisionNotes
1Loan officerMay 12, 2026 6:37 PMApprovedReviewed SoV and inspection. Approved.
2Owner developerMay 13, 2026 6:37 PMApprovedOwner sign-off complete.
3Finance reviewerMay 14, 2026 6:37 PMApprovedReleased $127,800 net of 10% retainage.
Payment releases
Finance reviewer records each release with reference and retainage breakdown.
ReleasedAmountRetainage heldMethodReference
May 14, 2026$127,800$14,200achACH-20260513-DR2031
Status timeline (6 transitions)
Every state change is logged with actor and reason.
  1. May 2, 2026 6:37 PM
    Draft
  2. May 4, 2026 6:37 PM
    DraftSubmitted
    GC submitted with 12 SoV lines + 5 waivers.
  3. May 8, 2026 6:37 PM
    SubmittedInspected
    Inspector recorded 85% complete.
  4. May 10, 2026 6:37 PM
    InspectedIn review
    Sent to loan officer for review.
  5. May 13, 2026 6:37 PM
    In reviewApproved
    Owner sign-off complete.
  6. May 14, 2026 6:37 PM
    ApprovedReleased
    Payment released $127,800.