DRDrawRequest
Demo mode
Active role: Lender admin
PROJ-2031 · Kim Development

Riverline Plaza

4200 Lakeshore Dr, Austin, TX · Start Mar 16, 2025 · Expected completion Nov 12, 2026

ActiveLoan LOAN-2031 · 7.25% APR · maturity Nov 12, 2027
Loan principal
$4,200,000
Drawn to date
$1,450,800
34.5% of principal.
Total requested
$1,612,000
5 draws on record.
Open draws
0
In flight.
Draw history (5)
Every draw on this project — requested, approved, released, retainage held.
#DrawGCRequestedApprovedReleasedRetainage heldReleased dateStatus
1DRAW-2031-P1Pinnacle Construction$315,000$315,000$283,500$31,500Apr 22, 2025Released
2DRAW-2031-P2Pinnacle Construction$350,000$350,000$315,000$35,000Jul 22, 2025Released
3DRAW-2031-P3Pinnacle Construction$385,000$385,000$346,500$38,500Oct 22, 2025Released
4DRAW-2031-P4Pinnacle Construction$420,000$420,000$378,000$42,000Jan 22, 2026Released
5DRAW-2031Pinnacle Construction$142,000$142,000$127,800$14,200May 14, 2026Released