PROJ-2022 · Eastside Industrial Park

DRAW-2070 — draw request

Crestline Contractors · Period Apr 16, 2026 – May 11, 2026

Approved (pending waivers)
2 missing waivers
Requested
$215,000
This draw period.
Approved
$215,000
Approved May 13, 2026
Released (net)
$0
Awaiting release.
Retainage held
$0
10% per draw.
Percent complete
72.0%
From inspector report.
Schedule of values (2 line items)
AIA G703-style schedule. Inspector validates percent-complete per line.
#CostDescriptionScheduledThis periodTo date%Balance to finishRetain
109000Drywall & finishes$120,000$60,000$95,00079%$25,000$6,000
206000Carpentry$95,000$40,000$70,00074%$25,000$4,000
Totals (2 lines)$215,000$100,000$165,00072.0%$50,000$10,000
Lien waivers (5)
Required from each subcontractor with paid work this period. Waivers older than 60 days expire.
SubTypeSignedAmount throughStatus
Phoenix Electrical
SUB-210 · electrical
Conditional progressMay 15, 2026$0Missing
Riverbend Plumbing
SUB-206 · plumbing
Conditional progressMay 15, 2026$0Missing
Ironclad Drywall
SUB-208 · drywall
Conditional progressMay 8, 2026$38,000Signed
Bluefield Sitework
SUB-209 · sitework
Conditional progressMay 8, 2026$24,000Signed
Cedar Finishes Inc
SUB-205 · finishes
Conditional progressMay 8, 2026$18,000Signed
Inspections (0)
Independent field validation of percent-complete claims by line.
No inspections recorded yet.
Approval chain
Loan officer → owner sign-off → finance releases. Senior lender required over $500,000.
StepRequired roleApproverDecidedDecisionNotes
1Loan officerMay 12, 2026 6:37 PMApproved
2Owner developerMay 13, 2026 6:37 PMApproved
3Finance reviewerAwaiting assignmentPendingAwaiting all required lien waivers.
Status timeline (0 transitions)
Every state change is logged with actor and reason.

    Loan reference: PROJ-2022 (Eastside Industrial Park) · principal $6,750,000. Active persona: Lender admin.