PROJ-2027 · Cypress Creek Office Park
DRAW-2050 — draw request
Westbrook GC · Period Apr 21, 2026 – May 15, 2026
1 open exception
- Variance over tolerance: Variance over tolerance: Foundation line claimed 80%, inspector observed 55% (25% variance, tolerance 5%).
Requested
$88,000
This draw period.
Approved
$0
Pending
Released (net)
$0
Awaiting release.
Retainage held
$0
10% per draw.
Percent complete
55.0%
From inspector report.
Schedule of values (1 line items)
AIA G703-style schedule. Inspector validates percent-complete per line. GC: SoV is editable while in draft / correction_required.
| # | Cost | Description | Scheduled | This period | To date | % | Balance to finish | Retain |
|---|---|---|---|---|---|---|---|---|
| 1 | 03000 | Foundation - concrete & rebarVariance (claimed 80.0%, observed 55.0%) | $180,000 | $44,000 | $99,000 | 80% | $81,000 | $4,400 |
| Totals (1 lines) | $180,000 | $44,000 | $99,000 | 55.0% | $81,000 | $4,400 | ||
Lien waivers (0)
Required from each subcontractor with paid work this period. Waivers older than 60 days expire.
| Sub | Type | Signed | Amount through | Status |
|---|---|---|---|---|
| No waivers attached yet. | ||||
Inspections (1)
Independent field validation of percent-complete claims by line.
Hank Mendez
Visited May 12, 2026 · 6 photos
55.0%
SubmittedWalked the foundation. Significantly less progress than claimed: only south footings poured; north & east still in forming.
Line findings
| Line | Claimed | Observed | Variance |
|---|---|---|---|
| SoV line | 80% | 55% | 25% |
Approval chain
Loan officer → owner sign-off → finance releases. Senior lender required over $500,000.
| Step | Required role | Approver | Decided | Decision | Notes |
|---|---|---|---|---|---|
| No approval steps generated. | |||||
Status timeline (4 transitions)
Every state change is logged with actor and reason.
- May 6, 2026 6:37 PMDraft
- May 9, 2026 6:37 PMDraft →SubmittedGC submitted DRAW-2050.
- May 12, 2026 6:37 PMSubmitted →InspectedInspector reported 55% vs claimed 80%.
- May 12, 2026 6:37 PMInspected →Correction requiredVariance > 5% tolerance.
Loan reference: PROJ-2027 (Cypress Creek Office Park) · principal $3,850,000. Active persona: Lender admin.