PROJ-2018 · Hawthorne Apartments

DRAW-2060 — draw request

Heartland Builders · Period Apr 26, 2026 – May 14, 2026

In review
Senior approval required
Requested
$620,000
This draw period.
Approved
$0
Pending
Released (net)
$0
Awaiting release.
Retainage held
$0
10% per draw.
Percent complete
62.0%
From inspector report.
Schedule of values (5 line items)
AIA G703-style schedule. Inspector validates percent-complete per line.
#CostDescriptionScheduledThis periodTo date%Balance to finishRetain
103000Foundation & slab$380,000$95,000$380,000100%$0$9,500
205000Structural steel$450,000$210,000$380,00084%$70,000$21,000
307000Roofing$180,000$85,000$120,00067%$60,000$8,500
415000HVAC rough-in$260,000$95,000$95,00036%$165,000$9,500
516000Electrical rough-in$195,000$50,000$50,00026%$145,000$5,000
Totals (5 lines)$1,465,000$535,000$1,025,00062.0%$440,000$53,500
Lien waivers (0)
Required from each subcontractor with paid work this period. Waivers older than 60 days expire.
SubTypeSignedAmount throughStatus
No waivers attached yet.
Inspections (0)
Independent field validation of percent-complete claims by line.
No inspections recorded yet.
Approval chain
Loan officer → owner sign-off → finance releases. Senior lender required over $500,000.
StepRequired roleApproverDecidedDecisionNotes
1Loan officerMay 12, 2026 6:37 PMApprovedApproved at loan officer level — escalating to senior lender (over $500k).
2Senior LenderAwaiting assignmentPendingSenior lender approval required (>$500k).
Status timeline (3 transitions)
Every state change is logged with actor and reason.
  1. May 8, 2026 6:37 PM
    Draft
  2. May 11, 2026 6:37 PM
    DraftSubmitted
    GC submitted DRAW-2060.
  3. May 12, 2026 6:37 PM
    SubmittedIn review
    Over $500k threshold; senior lender approval required.

Loan reference: PROJ-2018 (Hawthorne Apartments) · principal $8,500,000. Active persona: Lender admin.